[2.100][QUESTION] Release plan ?

Hi

Seems there are not too much activities now there... Do you plan to have a final release soon ?

thx
Parents
  • Good question BuBu, I'm also interested in this!

    And if there is a new Beta or RC1 release, will there be an Up2date packgae or do we have to do a fresh install?

    Thanks...
  • The roadmap i know is:

    ACC V2.1: Q4 2009 (so, should come soon...)
    ACC V2.2: Q1 2010
    ACC V3.0: Q3 2010

    I would also like to have an update instead of making  a new installation. (Also between beta/RC versiona)
  • Hi,

    current planning:


    • late this week or early next week: ACC V2.1 RC (2.070)
    • one week after RC, we will soft-release ACC V2.1 (2.100)
    • one week after soft-release, we will either confirm this version or issue a new GA with final fixes/adjustments
    • summing up: GA probably early December

    There will be two Up2Dates for the ACC V2.1 RC:


    • ACC 2.000 -> 2.070 (last stable to RC)
    • ACC 2.060 -> 2.070 (Beta to RC)

    Of course, the same will apply for the ACC V2.1 GA:


    • ACC 2.000 -> 2.100 (previous stable to new stable)
    • ACC 2.070 -> 2.100 (RC to GA)

    Regarding the roadmap information posted here:


    • This is internal/partner (only) information
    • Please do not post it within the UBB

    On the day of ACC V2.1 GA soft-release, the BETA contest will officially end. That means that the RC, although considered to be very mature and stable, might still contain bugs and/or other issues.

    Thanks and regards,
    Henning
Reply
  • Hi,

    current planning:


    • late this week or early next week: ACC V2.1 RC (2.070)
    • one week after RC, we will soft-release ACC V2.1 (2.100)
    • one week after soft-release, we will either confirm this version or issue a new GA with final fixes/adjustments
    • summing up: GA probably early December

    There will be two Up2Dates for the ACC V2.1 RC:


    • ACC 2.000 -> 2.070 (last stable to RC)
    • ACC 2.060 -> 2.070 (Beta to RC)

    Of course, the same will apply for the ACC V2.1 GA:


    • ACC 2.000 -> 2.100 (previous stable to new stable)
    • ACC 2.070 -> 2.100 (RC to GA)

    Regarding the roadmap information posted here:


    • This is internal/partner (only) information
    • Please do not post it within the UBB

    On the day of ACC V2.1 GA soft-release, the BETA contest will officially end. That means that the RC, although considered to be very mature and stable, might still contain bugs and/or other issues.

    Thanks and regards,
    Henning